Question: Joe used a project management software package and has determined the following results for a given project.: Expected completion time of the project = 22
Joe used a project management software package and has determined the following results for a given project.:
Expected completion time of the project = 22 days
Variance of project completion time = 2.77
What is the probability of completing the project over 20 days?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts