Question: Joe used a project management software package and has determined the following results for a given project: Expected completion time of the project - 22

Joe used a project management software package

Joe used a project management software package and has determined the following results for a given project: Expected completion time of the project - 22 days Variance of project completion time = 2.77 What is the probability of completing the project over 21 days? 0.8849 0.9649 0.2257 0.7257