Question: Jane produces custom cards using a 6-step production process as shown in the figure below. She would like to produce 10 cards in each 8
Jane produces custom cards using a 6-step production process as shown in the figure below. She would like to produce 10 cards in each 8 hour shift. What is the Cycle time required to satisfy the required output rate ?
Using Jane's Custom Cards process; What is the Theoretical Minimum number of work stations required?
Using Jane's Custom Cards process and 5 workstations what is the (1), efficiency and (2), the balance delay respectively: