Question: please draw diagram and chart, show answer P1. A project consists of 10 activities, lettered A through 1 , as shown in the sccompanying precedence
please draw diagram and chart, show answer
P1. A project consists of 10 activities, lettered A through 1 , as shown in the sccompanying precedence diagram, with the activities on the arrows. For each activity, the deterministic time estimate in weeks is shown in tha fall.wann arous a. List all of the paths through the network. b. What is the duration of each of the paths? c. What is the critical path? d. What is the second-most critical path? e. What is the slack time for each activity? f. Calculate the ES, EF, LS and LF times for each activity