Question: Jane produces custom greeting cards using six distinct work elements. She would like to produce 1 0 cards in each 8 - hour card -

Jane produces custom greeting cards using six distinct work elements. She would like to produce 10 cards
in each 8-hour card-making session. The figure to the right details each work element and its associated
durations in minutes as well as their precedence relationships.
a. What cycle time is required to satisfy the required output rate? 48 minutes/card.(Enter your response
as an integer.)
b. What is the theoretical minimum number of workstations required? 2 stations. (Enter your response
rounded up to the next whole number.)
c. If Jane identifies a four-station solution, what is the associated efficiency and balance delay? (Enter your
responses as percentages rounded to one decimal place.)
Efficiency:
%.
Balance delay:
%
 Jane produces custom greeting cards using six distinct work elements. She

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!