Question: Jim Johnston has been assigned as project manager for the Next Gen Widget project. Jim's organization believes pursuing the market for this product will provide

Jim Johnston has been assigned as project manager for the Next Gen Widget project. Jim's organization believes pursuing the market for this product will provide opportunities for expanding its current product offerings, as producing 'widgets' uses similar production techniques as its current product offerings. . Unfortunately, the organization has no experience in the 'widget' market. What tool or technique should Jim employ to gather requirements for the project