Question: jn Logic Problem #3: The Incomplete Status Report 45 As a continuation of Logic Problem #2, you also discover that the status report for your

jn
Logic Problem #3: The Incomplete Status Report 45 As a continuation of Logic Problem #2, you also discover that the status report for your project is somewhat incomplete. The status report is shown below. From the clues provided, complete the status report. Clues 1. For Activity B, PV = $100 2. For Activity C, EV = $200 3. For Activity D, AC = $300 4. Activity A has not started yet. 5. For all of the activities EV (Total) = 5930 Activity PV EV AC SV CV A (S100) 50 0 60 B c 60 60 D 100 120 80 (20) E Total Logic Problem #4: Another Mysterious Network Diagram A project manager discovers that his team has neglected to complete the network dia- gram for the project. The network diagram is shown below. However, the project man- ager has some information available, specifically that each activity, labeled A-G, has a different duration between one and seven weeks. Also, the slack time for each of the activities is known as shown below. Duration (weeks): 1, 2, 3, 4, 5, 6, 7 Slack time (weeks): 0,0,0,1,1,3,7 A B E GO START FINISH Using the clues provided below, determine the duration of each activity as well as the early start, early finish, latest start, and latest finish times for each activity Clues 1. Activity E is the longest-duration activity and is on the critical path, which is the unlucky number 13; also, there is only one critical path. 2. The early finish time (EF) for Activity F is eleven weeks. 3. The latest start time (LS) for Activity Dis nine weeks. 4. If Activity A slips by one week, it will be on a critical path. Early Start Early Finish Latest Start Latest Finish Activity Duration B D E F GStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
