Question: Job A, B, C, D, and E are waiting for our processing at the sawing work center. The processing times, number of operations, and due
Job A, B, C, D, and E are waiting for our processing at the sawing work center. The processing times, number of operations, and due dates for these jobs are provided below. Move and queue time is 2 days per operation remaining. Assume current time = 0
| Job | sawing Time | total processing time remaining (includes sawing) | total # of operations remaining (include sawing) | Due date |
| A | 7 | 15 | 3 | 20 |
| B | 3 | 10 | 2 | 18 |
| C | 5 | 14 | 3 | 16 |
| D | 2 | 12 | 3 | 19 |
| E | 3 | 10 | 2 | 16 |
In what sequence should these jobs be processed using the critical ratio priority rule. Show your work