Question: Job A B C D E A group of five jobs needs to go through a two-machine flow shop, in sequence. The first operation involves
Job A B C D E A group of five jobs needs to go through a two-machine flow shop, in sequence. The first operation involves grinding, and the second is deburring. Use Johnson's rule to find the optimum