Question: Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C
Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C & D. Which activity along the critical path has a slack time of 2 days?
a.
A
b.
B
c.
C
d.
D
e.
None of the above.