Question: Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C

Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 and immediate predecessors are -, A, B, B, and C & D. Which activity along the critical path has a slack time of 2 days?

a.

A

b.

B

c.

C

d.

D

e.

None of the above.