Question: Homework Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 respectively and immediate predecessors are: A has none, B

Homework

Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 respectively and immediate predecessors are: A has none, B needs A, C needs B, D needs B, E needs both C and D. What is the earliest completion time of D?

Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 respectively and immediate predecessors are: A has none, B needs A, C needs B, D needs B, E needs both C and D. Determine the critical path for this project.