Question: Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 respectively and immediate predecessors are: A has none, B needs
Job A, B, C, D, E with processing times (days): 8, 2, 4, 6, 7 respectively and immediate predecessors are: A has none, B needs A, C needs B, D needs B, E needs both C and D. Which activity along the critical path has a slack time of 2 days? Select one: a. A b. B c. C d. D e. None of the above.
An algebraic optimization problem must involve three variables. These include:
Select one:
a. Decision, objective, constraints
b. Constraints, probability, decision
c. Random, parameters, control
d. Decision, Random, constraints
e. Objective, Decision, parameters
A cashier at a department store can ring up 25 customers in every hour. About 15 customers enter the store every hour. What is the average waiting time for a customer before paying?
Select one:
a. 2 min.
b. 10 min.
c. 16 min.
d. 20 min.
e. None of the above