Question: JOB ABCDEF PROCESS TIME 15 15 18 9 16 23 DUE DATE 30 27 31 15 19 37 Sort these jobs according to Least Slack

JOB ABCDEF PROCESS TIME 15 15 18 9 16 23 DUE DATEJOB ABCDEF PROCESS TIME 15 15 18 9 16 23 DUE DATE

JOB ABCDEF PROCESS TIME 15 15 18 9 16 23 DUE DATE 30 27 31 15 19 37 Sort these jobs according to Least Slack (LS) 4. C 3. B 5. VF 1. E 2. D 6. A See the timeline (Gannt chart) of the single resource below. Job B Time (start....stop) ........12 12. D E 27 27. 1515.. ..25 25. .38 What is the Makespan? (just enter as a number, no time units needed) 38