Question: Job Processing time (Days) Job Due Date (Days) A 16 25 B 6 12 C 12 19 D 18 22 E 19 20 Five architectural
| Job | Processing time (Days) | Job Due Date (Days) |
|---|---|---|
| A | 16 | 25 |
| B | 6 | 12 |
| C | 12 | 19 |
| D | 18 | 22 |
| E | 19 | 20 |
Five architectural rendering jobs are waiting to be assigned at Avanti Architects. Their processing times and due dates are shown in the table. The firm wants to determine the sequence of jobs according to shortest processing time (SPT). Jobs are assigned a letter in the order day arrived. The utilization is _%. Today is day 1 and work begins today.