Question: JOB PROCESSING TIME DUE DATE A 24 10 B 8 5 C 9 12 D 3 4 E 6 8 F 5 18 Required Determine
| JOB | PROCESSING TIME | DUE DATE |
| A | 24 | 10 |
| B | 8 | 5 |
| C | 9 | 12 |
| D | 3 | 4 |
| E | 6 | 8 |
| F | 5 | 18 |
Required Determine the average job flow time the average tardiness, work in process inventory and utilization with the following priority rules:
A. Shortest processing time (3 points)
B. Due date processing time (3 Points)
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
Step 1 of 7 Sequencing is used to determine in which order jobs should be processed There are differ... View full answer