Question: Joe used a project management software package and has determined the following results for a given project: Expected completion time of results of project=22 days
Joe used a project management software package and has determined the following results for a given project:
Expected completion time of results of project=22 days
Variance of project of completion time = 2.77
What is the probability of completing the project within 20 days?
0.3849
0.8849
0.1151
0.7642