Consider the following table of activities A through G in which A is the start node and
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days) Predecessor A 10 -- B 20 A C 5 A D 3 B, C E 20 B, C F 4 B, C G 10 D, E, F On a piece of scratch paper, draw the network associated with this table and determine the following.
What kind of activity is activity B?
Non-critical activity only
Non-critical activity and burst activity
Critical activity and burst activity
Critical activity and merge activity