Question: John is the project manager for a software project. He and his team are determining the activity duration estimates for the project. John has requested
John is the project manager for a software project. He and his team are determining the activity duration estimates for the project. John has requested that each team member determine the estimates by multiplying the quantity of work to be performed by the historical productivity rate of the individual department. John has asked his team to generate the estimates using what technique? Select one: a. Expert judgment b. Three-point estimating c. Analogous estimating d. Parametric estimating