Question: John is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until the next
John is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until the next week. This is an example of what kind of resource constraint?
Select one:
A
People
B
Equipment
C
Information
D
Materials