Question: Question 6 1 points Save Answer Sam is trying to order the concrete needed to continue his project. However, the supplier won't be able to
Question
points
Save Answer
Sam is trying to order the concrete needed to continue his project. However, the supplier won't be able to deliver it until next week. This is an example of a constraint.
Working capital
People
Equipment
Information
Materials