Question: Sam is trying to order the concrete needed to continue his project. However, the supplier won't be able to deliver it until next week. This

Sam is trying to order the concrete needed to continue his project. However, the supplier won't be able to deliver it until next week. This is an example of a _______ constraint.
Group of answer choices
Working capital
Materials
Equipment
Information