Question: John, the GoodPMs Project Manager (PM), worked with his team to come up with estimates for various tasks, which are summarized in the following table.

John, the GoodPMs Project Manager (PM), worked

John, the GoodPMs Project Manager (PM), worked with his team to come up with estimates for various tasks, which are summarized in the following table. Answer the following question according to the information in this table. The task "Obtain Hardware" is: Task Name Start End Develop Plan 1 6 Assign tasks 3 3 6 Obtain Hardware 1 9 Programming 4. 20 Install Hardware 10 12 A successor of "Develop Plan" O A predecessor of "Install Hardware" A successor of "Assign Tasks" None of the above