Question: Johns Construction has three projects under way. Each project requires a regular supply of gravel, which can be obtained from three quarries. Shipping costs differ
Johns Construction has three projects under way. Each project requires a regular supply of gravel, which can be obtained from three quarries. Shipping costs differ from location to location, and are summarized in the table. From: Job 1 Job 2 Job 3 Tonnage Allowance Quarry A $9 $8 $7 1500 Quarry B $7 $11 $6 1750 Quarry C $4 $3 $12 2750 Job requirements (tonnes) 2000 3000 1000 6000 Formulate a transportation model (but do not attempt to solve it) which could be used to determine the amount of gravel to be shipped from each quarry to the various job sites