Question: Kata Systems allocates manufacturing overhead based on machine hours. Each connector should require 8 machine hours. According to the static budget, Kata expected to incur
Kata Systems allocates manufacturing overhead based on machine hours. Each connector should require 8 machine hours. According to the static budget, Kata expected to incur the following (Click the icon to view the static budget information.) During August, Kata actually used 500 machine hours to make 90 connectors and spent $5,000 in variable manufacturing costs and $8,800 in fixed manufacturing overhead costs Calculate the variable overhead efficiency variance for Kata A. $4,000F B. $1,500F C. $2,750F D. $1,250U