Question: Kata Systems allocates manufacturing overhead based on machine hours. Each connector should require 10 machine hours. According to the static budget, Kata expected to incur

Kata Systems allocates manufacturing overhead based on machine hours. Each connector should require 10 machine hours. According to the static budget, Kata expected to incur the following: 600 machine hours per month (60 connectors x 10 machine hours per connector) $7,500 in variable manufacturing overhead costs $5,325 in fixed manufacturing overhead costs During August, Kata actually used 500 machine hours to make 120 connectors and spent $5,300 in variable manufacturing costs and $9,100 in fixed manufacturing overhead costs. Kata's standard variable manufacturing overhead allocation rate is O A. $8.88 per machine hour. O B. $15.00 per machine hour. O c. $12.50 per machine hour. OD. $21.38 per machine hour