Question: Kim's engineering has a plan to build a new factory to expand their business. Consider the project with the following dependency matrix and the expected
Kim's engineering has a plan to build a new factory to expand their business. Consider the project with the following dependency matrix and the expected time for each activity.
| Activity | Predecessor | Activity Time (Month) |
| A1 | 3 | |
| A2 | A1 | 4 |
| A3 | A1 | 5 |
| A4 | A1 | 6 |
| A5 | A1 | 7 |
| A6 | A2, A3, A4 | 8 |
| A7 | A5, A6 | 9 |
| A8 | A7 | 10 |
a. Draw an activity network for the project b. Compute the total slack time of the project using EST, ECT, LST, LCT c. Draw a Gantt chart for the project