Question: Kim's engineering has a plan to build a new factory to expand their business. Consider the project with the following dependency matrix and the expected

Kim's engineering has a plan to build a new factory to expand their business. Consider the project with the following dependency matrix and the expected time for each activity.

Activity Predecessor

Activity Time (Month)

A1 3
A2 A1 4
A3 A1 5
A4 A1 6
A5 A1 7
A6 A2, A3, A4 8
A7 A5, A6 9
A8 A7 10

a. Draw an activity network for the project b. Compute the total slack time of the project using EST, ECT, LST, LCT c. Draw a Gantt chart for the project