Question: Kirby Builders, Inc. is using the completed-contract method for a $5,600,000 contract that will take two years to complete. Data at December 31, 2010, the
Kirby Builders, Inc. is using the completed-contract method for a $5,600,000 contract that will take two years to complete. Data at December 31, 2010, the end of the first year, are as follows:
cost inccured to date : 2,560,000
estimate cost to complete 3,280,000
billing to date 2,400,000
collection to date 2,000,0000
The gross profit or loss that should be recognized for 2010 is $0. a $240,000 loss. a $120,000 loss. a $105,600 loss.
a) 0
b) 240,000 loss
c) 120,000 loss
d) 105, 600 loss