Question: Knowing that you are learning a course on project management, a member of your family has asked you to prepare a professional-looking chart for a
Knowing that you are learning a course on project management, a member of your family has asked you to prepare a professional-looking chart for a home-building plan. He has provided you with a list of project tasks with durations (as found in the attached file).
1. Prepare a Gantt Chart for this project. Note that in the Gantt Chart, show the following:
- Project start date (as milestone) supposing that the project had begun on your most recent date of birth. Project finish date (as milestone).
- Organize the tasks into summary tasks and subtasks. Identify possible milestones. Assign possible resources to tasks.
- Create links between tasks.
- Save the project as baseline. The project task Make a budget was completed by 50 percent. Show the progress of the task (how much has been accomplished?)
2. What is the overall completion time of the project?
| Make a budget | 30 days |
| Home plans | 1 day |
| Prepare the house drawing plan | 20 days |
| Prepare specifications (discription of materials, equipments used,) | 10 days |
| Approve the plan | 0 days |
| Approve specifications | 0 days |
| Building permit | 1 day |
| Prepare necessary documentation | 30 days |
| Seek appraisal and approval of the building permit | 15 days |
| Building permit issued | 0 days |
| Contracts & scheduling | 1 day |
| Find a qualified contractor | 7 days |
| Prepare construction documents required to fulfill the contract | 10 days |
| Sign the contract | 1 day |
| Prepare the construction schedule | 7 days |
| Site preparation | 1 day |
| Prepare temporary accomodations | 3 days |
| Lay out the house from the plot plan | 1 day |
| Grading | 2 days |
| Excavate for a basement | 1 day |
| Foundation | 1 day? |
| Erect forms | 3 days |
| Pour concrete (including waiting time for concrete to dry) | 20 days |
| Remove forms | 1 day |
| Foundation certification | 0 days |
| Framing | 1 day? |
| Install floor joists | 3 days |
| Install sub-flooring | 2 days |
| Erect stud walls | 2 days |
| Frame roof | 5 days |
| Install doors and windows | 2 days |
| Utilties | 1 day? |
| Electrical | 1 day? |
| Rough in | 5 days |
| Building inspection | 6 days |
| Plumbing | 1 day? |
| Rough in | 5 days |
| Building inspection | 1 day |
| Gas | 1 day? |
| Rough in | 3 days |
| Building inspection | 0 days |
| Rough-ins complete | 0 days |
| Walls | 1 day? |
| Hang drywall | 3 days |
| Tape and fininsh drywall | 10 days |
| Painting | 6 days |
| Roofing | 1 day? |
| Install sheathing | 3 days |
| Lay shingles | 5 days |
| Install appliances | 4 days |
| Final inspection | 0 days |