Question: Amir was originally assigned to a Fixed Du ation Task that was estimated to take 3d of Duration to complete. This equates to 24 hours

Amir was originally assigned to a Fixed Du ation
Amir was originally assigned to a Fixed Du ation Task that was estimated to take 3d of Duration to complete. This equates to 24 hours of Work at 100%. Amir has reported that it will take him 32 hours to complete the task. What happens to Duration, Work, and Units when the hours of Work is changed to 32 hours and you press OK. What does the red man indicator mean? Duration =3d, Work =32h, Units = 133% Amir is overallocated Duration =4d, Work =32hours, Units = = 100% Amir is not overallocated Duration =2d, Work =32hours, Units = =200% Amir is crazy. Duration=3d Work =24 h, Units = 100% Amir gets the job done

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!