Question: Konsider the network diagram and table below. All durations are in days. table [ [ , Time ( days ) , Cost ( $

Konsider the network diagram and table below. All durations are in days.
\table[[,Time (days),Cost ($),],[Activity,Normal,Crash,Normal,Crash,Crash Cost Per Day],[A,3,2,1000,1200,],[B,6,4,1500,1800,],[C,7,6,1000,1100,],[D,5,4,1200,1600,],[E,4,\table[[Not],[possible]],1000,\table[[Not],[possible]],]]
A) What is the critical path?
B) To shorten the project from 12 to 11 days, what activity should be crashed and what is the cost of crashing?