Question: Kumar is a project manager working in the washing machine industry. He is performing quality control and wants to rank order the frequency of production

Kumar is a project manager working in the washing machine industry. He is performing quality control and wants to rank order the frequency of production delay and motor defects. Which of the following tools or techniques should he utilize? Scatter diagram Pareto Chart Control chart Fishbone diagram