Question: L 0 1 9 - 4 5 . A project activity has an earliest completion time of 5 , an activity time of 3 ,

L019-4
5. A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?
a.1
b.2
c.3
d.4
e.5
f.6
 L019-4 5. A project activity has an earliest completion time of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!