A project activity has an earliest completion time of 5, an activity time of 3, and a

Question:

A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity? 

a. 1 

b. 2 

c. 3 

d. 4 

e. 5 

f. 6