Question: Lab exercise 1: 15 You are a project manager for a new project Lab Exercise 1 with Gantt chart using ProjectLibre with the following information.

Lab exercise 1: 15 You are a project manager for

Lab exercise 1: 15 You are a project manager for a new project Lab Exercise 1" with Gantt chart using ProjectLibre with the following information. Task Duration (days) Dependencies T1 T2 8 T3 20 T1 T4 5 5 T2, T4 T6 10 T1,T2 T7 25 T1 T8 75 T4 T9 10 T3, T6 T10 20 T7, T8 T11 10 T9 T12 20 T10, 111 T5 In addition, T1 until T4 are tasks under Phase 1. Other tasks are planned in Phase 2. Only relevant 3 columns and the Gantt Chart should be displayed. Submit your work in PDF format