Question: Latest start time is calculated by adding the activity s estimated duration to the activity s latest finish time: LS = LF + Estimated Duration.

Latest start time is calculated by
adding the activitys estimated duration to the activitys latest finish time: LS = LF + Estimated Duration.
subtracting the activitys estimated duration from the activitys latest finish time: LS = LF Estimated Duration.
subtracting the activitys estimated duration from the activity's succeeding activitys latest finish time: LS = LF succeeding activity Estimated Duration.
adding the activitys estimated duration to the predecessor of the activitys latest start time: LS = LS predecessor + Estimated Duration.