Question: Lead time for cakes is 2 days with daily demand of 5 cakes and a safety stock of (1)/(2) day. Each container (kanban) holds 2
Lead time for cakes is 2 days with daily demand of 5 cakes and a safety stock of (1)/(2) day. Each container (kanban) holds 2 cakes. What is the correct number of kanbans? 5 6 4 10