Question: Lead time for cakes is 2 days with daily demand of 1 0 cakes and safety stock of ( 1 ) / ( 2 )

Lead time for cakes is 2 days with daily demand of 10 cakes and safety stock of (1)/(2) a day. Each container (kanban) holds one cake. What is the correct number of kanbans?
Answer
25
10
1