Question: Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish times for each activity Identify the critical path Activity

Lecture Exercise #12 Critical Path Method

Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish times for each activity Identify the critical path Activity Time (days) Predecessor(s) A None O 6 None 7 B 3 D 2 4 A A B E F 6 B G 10 C, E D, F H 7