Question: Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish times for each activity Identify the critical path Activity

Lecture Exercise #12 Critical Path Method
Lecture Exercise #12 Critical Path Method Determine the early start, early finish, late start, late finish times for each activity Identify the critical path Activity Time (days) Predecessor(s) 6 None B 7 None 3 A D 2 E 4 B F 6 B G CE 10 7 H DF