Let us revisit the project data are in days (and it is understood that the duration...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Let us revisit the project data are in days (and it is understood that the duration of activity A can be no less than 3 days, in which case it costs $150 instead of $50, and so on and so forth). where all times Normal Normal Crashed Crashed Predecessors Activity A Time Cost Time Cost $50 3 $150 В 4 40 2 200 В 7 70 160 A,C А,С В 2 20 1 50 E 3 30 F 8. 80 5 290 50 4 100 H E,F 60 3 180 The project has been sold at a fixed price to the client provided the project is completed on time, but in case of delays, there is a penalty of $100 for each day in excess of the normal completion time. Work on the project started on time, and the project manager scheduled a meeting with the supervisors in the morning of day 9 in order to monitor progress by the end of day 9 (time now). a) According to the normal project schedule, indicate what percentage of each activity should be completed by the end day 9. b) Suppose the progress reports indicate that activity A was completed on time but activity B will actually take 5 days longer than planned. Indicate what percentage of each activity will actually be completed by the end of day 9. c) Using the crash data, find the optimal way of rescheduling the remainder of the project. What is the revised expected project duration? And revised cost? Let us revisit the project data are in days (and it is understood that the duration of activity A can be no less than 3 days, in which case it costs $150 instead of $50, and so on and so forth). where all times Normal Normal Crashed Crashed Predecessors Activity A Time Cost Time Cost $50 3 $150 В 4 40 2 200 В 7 70 160 A,C А,С В 2 20 1 50 E 3 30 F 8. 80 5 290 50 4 100 H E,F 60 3 180 The project has been sold at a fixed price to the client provided the project is completed on time, but in case of delays, there is a penalty of $100 for each day in excess of the normal completion time. Work on the project started on time, and the project manager scheduled a meeting with the supervisors in the morning of day 9 in order to monitor progress by the end of day 9 (time now). a) According to the normal project schedule, indicate what percentage of each activity should be completed by the end day 9. b) Suppose the progress reports indicate that activity A was completed on time but activity B will actually take 5 days longer than planned. Indicate what percentage of each activity will actually be completed by the end of day 9. c) Using the crash data, find the optimal way of rescheduling the remainder of the project. What is the revised expected project duration? And revised cost?
Expert Answer:
Answer rating: 100% (QA)
Step 1 Introduction Given data is Step 2 Project network The network diagram for the given project d... View the full answer
Related Book For
Statistics The Art and Science of Learning from Data
ISBN: 978-0321755940
3rd edition
Authors: Alan Agresti, Christine A. Franklin
Posted Date:
Students also viewed these general management questions
-
Given the project within the table below calculate a. The critical path b. The minimum project duration c. The amount of slack for each activity Activity Duration (hours) Immediate Predecessors A 4...
-
It is desired to monitor project completion times by analysts in a consulting company. The magnitude and complexity of the project influence the completion time. It is also believed that the...
-
A CPM/PERT project network has probabilistic activity times (x) as shown on each branch of the network; for example, activity 13 has a .40 probability that it will be completed in 6 weeks and a .60...
-
The Secretary of Defense shall establish which program to maintain liaison with industry advisory groups to coordinate the development of the supply catalog?
-
Complete the following table by indicating whether the transactions or economic events would increase, decrease, or have no effect on the financial ratios listed. Consider each item independently....
-
A particle moves along a straight line such that its position is defined by s = bt 2 + ct + d. Determine the average velocity, the average speed, and the acceleration of the particle when t = t 1 ....
-
A long, thin metal plate is hung vertically after a heat treating process. The plate, of width \(W=0.2 \mathrm{~m}\), vertical dimension of \(3 \mathrm{~m}\), and an initial temperature of...
-
Lap Dogs Inc. is planning for next year and has the following summarized results so far ($000): Income Statement EBIT ..........236 Interest ...........? EBT ............? Income tax .........? EAT...
-
A soft tennis ball is dropped onto a hard floor from a height of 1.95 m and rebounds to a height of 1.56 m. (Assume that the positive direction is upward.) (a)Calculate its velocity (in m/s) just...
-
Figure 4-32 shows a class list for Millennium College. Convert this user view to a set of 3NF relations using an enterprise key. Assume the following: ¢ An instructor has a unique location....
-
A T-bill with face value $10,000 and 81 days to maturity is selling at a bank discount ask yield of 2.8% Required: 6. What is the price of the bill? (Use 360 days a year. Do not round intermediate...
-
What is a manufacturing network?
-
The value of a payment depends on when it is made. a. Future value is the present value of an initial investment times one plus the interest rate for each year you hold it. The higher the interest...
-
Explain the role of the customer in a total quality setting.
-
Give a brief rationale for empowerment.
-
Jane and Mike purchase identical houses for $400,000. Jane makes a down payment of $80,000, while Mike puts down only $20,000; for each individual, the down payment is the total of his or her net...
-
Explain the difference between valuing and managing diversity and provide examples from professional experiences for each. Your examples should be novel (do not use what is written in the book). Show...
-
1. What are some current issues facing Saudi Arabia? What is the climate for doing business in Saudi Arabia today? 2. Is it legal for Auger's firm to make a payment of $100,000 to help ensure this...
-
For the Georgia Student Survey file on the text CD, the prediction equation relating y = college GPA to x1 = high school GPA and x2 = study time (hours per day), is = 1.13 + 0.643x1 + 0.0078x2. a....
-
In one lottery option in Canada, you bet on a six-digit number between 000000 and 999999. For a $1 bet, you win $100,000 if you are correct. The mean and standard deviation of the probability...
-
Eighth-grade math scores on the National Assessment of Educational Progress had a mean of 277 in Nebraska compared to a mean of 271 in New Jersey (H. Wainer and L. Brown, American Statistician, vol....
-
A drainage ditch is to be built to carry runoff from a subdivision. The maximum design capacity is to be $1 \mathrm{million} \mathrm{gph}(\mathrm{gal} / \mathrm{h})$ and it is to be concrete lined....
-
An open drainage canal with a rectangular cross section is $3 \mathrm{~m}$ wide and $1.5 \mathrm{~m}$ deep. If the canal slopes $950 \mathrm{~mm}$ in $1 \mathrm{~km}$ of length, what is the maximum...
-
An open drainage canal is to be constructed to carry water at a maximum rate of $10^{6} \mathrm{gpm}$. The canal is concrete lined and has a rectangular cross section, with a width that is twice its...
Study smarter with the SolutionInn App