Question: Let's dive into a specific process at the ice cream shop for this and the remaining questions. The manager is trying to better understand the

Let's dive into a specific process at the ice cream shop for this and the remaining questions.
The manager is trying to better understand the way that milkshakes are made. They would like your help in line balancing the milkshake-making process. Info about the process included as follows. It may be helpful to try to create a process flow diagram that clearly outlines the precedence relationships involved.
Label
Task
Predecessor(s)
Time (seconds)
A
Gather ingredients
None
25
B
Measure milk
A
35
C
Measure ice cream
A
20
D
Pour ingredients into blender cup
B, C
40
E
Blend
D
60
F
Pour into glass
E
15
G
Clean station
F
55
H
Deliver to customer
F
20
Total Time
270
Assume a 12-hour shift (and, for simplicity's sake, assume that customers are only ordering milkshakes during this shift). If you have a customer demand of 675 milkshakes, what is your takt time (in seconds) for this shift? Round your answer to the nearest second.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!