Question: Let's say this is a project with 4 activities. Please perform as requested based on given information. Use the dropdowns to identify if each activity
Let's say this is a project with 4 activities. Please perform as requested based on given information. Use the dropdowns to identify if each activity is over budget or not. Y or N. Use the dropdowns to identify if each activity is behind schedule or not. Y or N. (Total of 8 blanks to fill) Tasks Planned Progress (%) Actual Progress (%) BAC ($) AC ($) Over Budget? (Y or N) Behind Schedule? (Y or N) A 100% 90% 10,000 6,000 [ Select ] [ Select ] B 50% 60% 20,000 14,000 [ Select ] [ Select ] C 30% 30% 30,000 7,000 [ Select ] [ Select ] D 10% 5% 40,000 5,000 [ Select ] [ Select ]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
