Question: Let's say we have a project with two tasks, building a fence and laying sod. The initial cost baseline is: ID Task 100 Build
Let's say we have a project with two tasks, building a fence and laying sod. The initial cost baseline is: ID Task 100 Build Fence 200 Lay Sod TOTAL Start date End Date Budget Feb. 10 Feb. 20 $4,000 Feb. 12 Feb. 25 $3,000 $7,000 Determine the percent complete for task of building the fence. Using the information given to you in determine the Earned value (EV) for the task of laying sod.
Step by Step Solution
3.46 Rating (159 Votes )
There are 3 Steps involved in it
Solution To determine the percent complete for the task of building the fence we need to compare the current progress of the task to its scheduled dur... View full answer