Lewis Noodles has the following cooking procedures. You will need to compute the cycle time per day
Fantastic news! We've Found the answer you've been seeking!
Question:
Lewis Noodles has the following cooking procedures. You will need to compute the cycle time per day and the minimum number of workstations assuming eight working hours a day and500units need to be made per day.
TASK DESCRIPTION TASK TIME PRECEDING TASK
A Cook vegetables 2 minutes
B Cut noodles 1 minute A
C Cook noodles 5 minutes B
D Cook meat 3 minutes C
E Mix ingredients 1 minute D
--------------