Question: list table [ [ Activity , ES , EF ] , [ A , 0 , 5 ] , [ B , 0 ,
list
tableActivityESEFABCDEFGH
Dave's latest start LS and latest finish LF are:
tableActivityLSLFHGFEDCBA
The slack times are:
tableActivitySlackAB
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES EF LS LF and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
tableActivityTime weeksImmediate PredecessorsActivity,Time weeksImmediate PredecessorsABBF