Question: ln the latest earned value report for your project, you see the CPI is 1.2, the SPI is 0.8, the PV is $600,000, and the
ln the latest earned value report for your project, you see the CPI is 1.2, the SPI is 0.8, the PV is $600,000, and the SV is -$120,000. You can't find the CV in the report, so you need to calculate it based on the information given. What is the CPI?