Question: Loading Charts Example No. Dur. Pred. Resources 1 2 NA EE (electrical engineer) 2 4 NA EE 3 3 NA ME (mechanical engineer) 4 1

Loading Charts Example No. Dur. Pred. Resources 1
Loading Charts Example No. Dur. Pred. Resources 1 2 NA EE (electrical engineer) 2 4 NA EE 3 3 NA ME (mechanical engineer) 4 1 1 EE 5 6 4 ME 6 2 2 ME 7 4 3 EE First ignoring the resourcing, do the AON CP method (draw the network, slacks) What is the duration of the project? Assume 1 of each resource at any one time. Populate a resource loading chart- similar to the below. Now what is the duration of the project? Create a resource activity schedule. EE ME