Question: a Based on the network below, create a loading schedule. You can shade the squares or write in them. Whatever you like. Each activity has

a Based on the network below, create a loading

a Based on the network below, create a loading schedule. You can shade the squares or write in them. Whatever you like. Each activity has a certain number of resources required. EE = Electrical Engineer and ME = Mechanical Engineer = 1 2 3 4 5 6 7 8 9 10 11 12 Res EE ME The duration for each activity is located in the middle bottom square. - 1 10 121 2 4 13 5 9 3 2 0 0 EE 0 1 EE 0 0 ME 0; 0 2 2 2 NI 1 6 9 3 D 2 2 4 4 6 6 3 EE 3 3 ME 3 34 7 7 N 9 0 3 3 3 3 7 7 2 ME 2 EE 2 N 2 3 5 5 4 9 I F 1 of 1 66 words Focus E =