Question: Loans are evaluated in a process with two resources. The first resource has a capacity of 0 . 1 6 loans per minute. The capacity

Loans are evaluated in a process with two resources. The first resource has a capacity of 0.16 loans per minute. The capacity of the second resource is 0.33 loans per minute. Demand for this process is 0.13 loans per minute.
Instruction: Round your answer to three decimal places.
What is the cycle time of this process (in seconds)?
;econds