Question: 2 Loans are evaluated in a process with two resources. The first resource has a capacity of 3.5 loans per hour. The capacity of the

2 Loans are evaluated in a process with two
2 Loans are evaluated in a process with two resources. The first resource has a capacity of 3.5 loans per hour. The capacity of the second resource is 3.2 loans per hour. The first resource has 10 workers and the second resource has 12 workers One additional worker is hired who is as productive as the current workers InstructionRound your answer to three decimal places What is the new capacity of this process? loans per hour 3 001828